BIM Life Cycle Information Management Platform of Shanghai North Cross Passage Project

Project introduction:The new project of beiheng passage is 19.1km across six central administrative districts of Shanghai, passing through 101 control buildings and structures, 11 crossing rail transit and 12 crossing river channels.。

Project features

The mode of information transmission has changed from the traditional point-to-point to the centralized sharing mode, which improves the fine management level of municipal engineering projects.

Based on the overall management of BIM consulting and 3DGIS + BIM platform, the collaborative management of municipal infrastructure projects in megacities is realized.

At present, the model data volume is 80GB for the main model of municipal engineering; 5GB for 40000 m² surrounding environment; 1.5GB for 15km municipal pipeline; 40km² for GIS satellite image and 20GB for model.

Platform implementation: 161 registered persons, 274 letters and visits, 723 progress records, 108 safety notices, 137 quality notices, 143 tengdi information management offices and 621 documents sharing.